On South San Francisco's Aquatics page, the November schedule looks routine. Lap swim starts at 5:30 a.m. on weekdays, the weekend adult swim runs until 12:30 p.m., and the pool closes for Thanksgiving weekend. Further down the same page are three lines that are not routine. All Session 2 swim lessons have been canceled. Orange Pool has stopped accepting rental applications "due to the upcoming transition and opening of the new Aquatic Center." And the City says it will post any schedule or registration updates there "as we prepare for the facility's opening."
Orange Pool opened in 1970 and is still the city's only indoor municipal pool. Its programs are being wound down as if the replacement is weeks away. The City's own contracts, though, now put the end of construction in early 2027. Those two facts together explain what swimmers can expect this fall and winter.
The old pool has already started cutting programs
Pool staff have already stopped taking on new commitments. Fall Session 1 lessons went ahead, with registration on September 9 for residents and September 16 for nonresidents. The City canceled Session 2 completely. The Fall 2026 Activity Guide had already called both the fall classes and the drop-in schedule tentative because of the new center's opening. If you planned a birthday party at Orange Pool, the City isn't booking rentals there now.
Drop-in swimming is still running. These are the closures and early closures posted for the rest of November:
- Wednesday, November 11: Pool closed
- Saturday, November 14: Pool closes at 8:30 a.m. after lap swim, no Rec Swim
- Wednesday, November 25: Pool closes at 3:00 p.m., no evening Lap/Rec Swim
- Thursday, November 26 through Sunday, November 29: Pool closed
These are ordinary holiday-season closures. The City's project FAQ says the switch itself will need a separate step. Orange Pool will likely close for a short period before the new building opens to the public, so staff can move in, train, test the building's systems and get the center ready. Any swimmer who uses Orange Pool every week will have a stretch with no city pool at all, and the Aquatics page is where its dates will appear.
The City's documents give different finish dates
The project FAQ says the new aquatic facility is "anticipated to open in late 2026." The July 23 construction update said the overall schedule had been extended and that staff were working on a recovery schedule with the contractor. It also said Phase 1 was still expected to finish in the fourth quarter of 2026.
A month later the City Council voted on the project. On August 26, 2026, it approved third amendments to two project contracts, and the two Council resolutions use the same wording. Each says the construction schedule "has been extended, with substantial completion and project closeout now anticipated in early 2027."
| Contract | August 26 amendment |
|---|---|
| ELS Architecture + Urban Design, architectural design services | Up to $211,429 |
| Swinerton, construction management | $483,945 |
The staff report says the project is still within its approved $49.8 million budget. The money comes from the Measure W bond sale in 2022. The extra contract money pays for the extra months of design and construction-management work. It doesn't add anything to the building.
The work listed in the July update describes a building near the end of construction. Drywall, wall tile and flooring were going in throughout. Synthetic turf was down on the outdoor recreation deck. Construction trailers had been removed so the lawn between the center and Colma Creek could be built. PG&E had issued the permanent power "green tag," which lets the final electrical connections go ahead.
Two pools at two temperatures
The new building is a single story of 24,000 square feet at 1 West Orange Avenue, built next to the old pool so swimming could continue during construction. One pool replaces the single tank at Orange Pool, which handled lap swimmers, toddlers and therapy sessions all at once. The other is new.
| Lap pool | Teaching and recreation pool | |
|---|---|---|
| Setting | Outdoors, behind wind screening | Indoors |
| Water temperature | About 78 to 80 degrees | About 83 degrees, close to Orange Pool today |
| Built for | 25-yard laps, full-course water polo with deck-mounted goals | Lessons, recreation, therapy |
| Entry | ADA lift | ADA lift, sloped entry with handrails |
| Markings | 25-yard and 25-meter | 25-yard |
The design also includes a beach entry, which the FAQ says is wanted for learn-to-swim programs, water play and swimmers who have difficulty using lifts or steps. Both pools will have starting blocks where the water is deep enough for lap and competitive swimming. The design also responds to complaints about the cramped locker rooms at Orange Pool. The FAQ says the new locker rooms are larger than typical for a facility this size. There are two sets of men's and women's locker rooms, one opening onto the outdoor deck, plus two gender-neutral family changing rooms. One of those has an adult-sized changing table. The indoor pool will use UV as a second disinfection system to cut down the chlorine byproducts that cause the familiar indoor-pool smell.
Why the outdoor pool has no roof
The FAQ answers the questions residents kept asking, and the answers mostly come down to cost. Putting a roof over the outdoor pool would cost about $1,000 per square foot, or roughly $42 million more. That is nearly as much again as the $49 million project budget. Wind screening is the City's answer to the wind instead. Prevailing winds in South San Francisco come from the northwest, so the heaviest screening runs along those edges of the deck, with lighter screening on the east side.
Other features were cut too:
- A 50-meter pool would have taken lawn space used for soccer and events, needed more parking and cost more to build.
- Diving boards need deep water, which would have meant extra soil stabilization the budget didn't cover. They also ranked lower than other features in community surveys.
- A sauna raised health and safety concerns and would have needed staff to supervise it, so outreach priorities went to other programs.
The park changes again after opening day
Opening day doesn't finish the project. Once the new center opens, the old Orange Pool building will be torn down to make room for parking and park features. The City expects the whole project, including demolition, a new parking lot and the relocated Veterans Memorial, to be complete in early 2027. The new lot will have 13 spaces, 6 of them wheelchair accessible, in addition to the Tennis Drive Parking Lot.
The Eternal Flame sculpture and the commemorative plaques will move to a new Veterans Memorial along the path between the aquatic center, the Fernekes Building and the playground. The new memorial will have its own flagpole, lighting, a wall with room for future plaques, accessible paving and seating. Some of the building's art was made by residents. On August 15, artist team Rachel Rodi and Guy Fuerte ran a workshop at the Joseph Fernekes Recreation Building at 781 Tennis Drive, where volunteers helped make a permanent community mosaic for the new center.
If Orange Memorial Park is already part of your weekend, our guide to parks and the waterfront in South San Francisco covers the rest of the city's open space.
What swimming costs now, and what renting the new building will cost
Prices on the November 2 to 25 drop-in schedule at Orange Pool:
- Adults: $6.50 resident, $9.00 nonresident
- Children, seniors and veterans: $4.50 resident, $6.00 nonresident
- 10-use and monthly passes are also sold
The City's adopted FY 2026–27 master fee schedule already has rental rates for the new building, so you can see what a party there will cost:
| New Aquatic Center rental | Rate |
|---|---|
| Indoor pool, up to 30 guests | $150.50 per hour |
| Outdoor pool | $215 per hour |
| Recreation swim package | $200 per hour |
| Multipurpose room | $113 per hour |
| Turf area | $43 per hour |
| Nonresident add-on | $41 per hour |
| Refundable damage deposit | $500 to $1,000 |
The City posts schedule changes, registration dates and the transition closure on its Aquatics page. Construction updates are on the New Aquatic Center project page, and the City answers questions sent to [email protected].
At Bryan Cruz and Rey Ancheta, we're keeping an eye on Orange Memorial Park as the new pools open, the old building comes down and the Veterans Memorial moves. If you own a home near the park and want to know how changes like these figure into its value, start with our instant home valuation. We're glad to talk it through in English, Tagalog or Ilocano.